The work, a major milestone for the project, will help pave the way for the arrival of the specialist tunnelling teams on site next year.
At Euston, HS2 will deliver 11 new platforms in two phases. This will more than double capacity at the station, as well as providing a new concourse and expanded Underground station, linked for the first time, to the nearby Euston Square tube station.
Twin 13 mile (21 kilometre) long tunnels, the biggest tunnelling project since Crossrail, will take the 360 km/h trains out of London via a new station at Old Oak Common linked to Crossrail. At the southern end, a tunnel portal will be built on the site of the carriage sheds, just south of Mornington Street Bridge.
The demolition, which took 9 months to complete was managed by HS2’s London enabling works contractor, CSJV working with demolitions contractor Keltbray. Up to 70 people were employed on site during the painstaking demolition of the sheds, which are adjacent to the west coast mainline.
Timelapse of HS2’s Euston tunnel portal site clearance
Specialist teams used drones to survey the inside of the Victorian structure, before taking the fragile roof structure apart. In total, more than 7,000 glazing panels had to be removed from the 250 metre long building. The team then used a cranes to remove the 27 huge 50 metre long steel trusses which supported the ceiling.
Out of use since 2004, the sheds were built to house carriages and later used for Royal Mail trains. Surplus track, switches and points removed from the sheds have been donated to the Bluebell railway, a heritage line in Sussex.
Welcoming the progress, HS2’s London Programme Director, Rob Carr, said:
The demolition of the old carriage sheds marks an important step forward for the project, clearing the way for the start of construction works next year, and the delivery of one of the most exciting new stations on the HS2 route. I’d like to congratulate the team on a job well done and look forward to moving ahead to the next stage of the project.
Peter Jones, CSJV Programme Director, said:
The CSJV team, consisting of people employed from the local area and other experienced professionals, alongside Keltbray have worked carefully and efficiently to ensure that this structure has been demolished safely. It marks a great milestone in the construction of HS2 and shows the fantastic progress that we are making in Euston and across Area South.
Press and media enquiries
For enquiries during office working hours, Monday to Friday, 9am to 5pm
020 7944 6149
For enquiries outside of these hours and at the weekend
020 7944 0550
The press and media enquiries line is for accredited journalists only
Link: Press release: First look at HS2’s Euston tunnel portal site
Source: Gov Press Releases