Press release: Report 09/2018: Freight train derailment at Ely West Junction

R092018_180802_Ely_West_Junction

This file may not be suitable for users of assistive technology.
Request an accessible format.

If you use assistive technology (such as a screen reader) and need a
version of this document in a more accessible format, please email enquiries@raib.gov.uk.
Please tell us what format you need. It will help us if you say what assistive technology you use.

Summary

At 14:21 hrs on Monday 14 August 2017, the rear 12 wagons of a freight train carrying containers derailed at Ely West Junction on the line between Ely and March. The train was travelling at 41 mph (66 km/h) at the time of the derailment. It ran derailed for approximately 350 metres, causing significant damage to the infrastructure.

The first wagon to derail was an FEA-A wagon fitted with Y33 bogies. The derailment occurred because the damping on the bogies of this wagon was ineffective. The damping had become ineffective because the damping components, which had been on the wagon since it was built in 2003, had been managed to incorrect maintenance limits. The limits did not account for future wear in the period before the next maintenance intervention and were also not compatible with the design intent of the damping system. In addition, the maintenance interventions since a General Repair in 2010 (the last time when these components had been measured) were ineffective in identifying the worn state of the components. It is also probable that the company responsible for the maintenance of the wagon did not appropriately validate the General Repair maintenance specification used in 2010 to confirm that it would ensure continued safe operation up to the next planned General Repair due in 2017.

The fleet of wagons has since gone through General Repair and all of the damping components have been replaced.

Recommendations

The RAIB has made one recommendation to the company responsible for the maintenance of the wagons to review its maintenance documentation to ensure that the bogies on its freight wagons remain adequately damped at all times. In addition, the RAIB has identified three learning points. The first reminds those responsible for updating maintenance instructions that repair limits quoted in guidelines or by manufacturers should not be used as maintenance limits as this provides no future operational life. The second learning point reminds Entities in Charge of Maintenance that they should have a validated system of maintenance that ensures that the vehicles for which they are in charge remain safe for operation. The final learning point reminds maintainers of this type of bogie that some of them are fitted with an inspection window to allow the damping system components to be visually examined.

Notes to editors

  1. The sole purpose of RAIB investigations is to prevent future accidents and incidents and improve railway safety. RAIB does not establish blame, liability or carry out prosecutions.
  2. RAIB operates, as far as possible, in an open and transparent manner. While our investigations are completely independent of the railway industry, we do maintain close liaison with railway companies and if we discover matters that may affect the safety of the railway, we make sure that information about them is circulated to the right people as soon as possible, and certainly long before publication of our final report.
  3. For media enquiries, please call 01932 440015.

Newsdate: 2 August 2018


Link: Press release: Report 09/2018: Freight train derailment at Ely West Junction
Source: Gov Press Releases

Press release: Come along to flood scheme update at Forge Mill Farm

If you are planning a visit to Sandwell Valley Park, Forge Mill Farm or RSPB on Thursday 9 August, why not come and talk to Environment Agency staff about the Perry Barr and Witton Flood Risk Management Scheme?

Environment Agency staff will be setting up a stall near the Forge Mill Farm car park on 9 August, from 1pm to 4pm, to talk to local residents and visitors about the progress being made.

The completed scheme will reduce flood risk for 1,400 properties in the area. Phase 2 of the scheme, will provide additional flood storage at Forge Mill in Sandwell Valley, which is upstream of Perry Barr and Witton, and will control the flow of flood water downstream. Park users will have seen construction happening around Forge Mill Farm, at the golf course and along the river side.

Rachel Kelly, Environment Agency Project Manager for the Scheme said:

This is a great opportunity to find out more about what we’ve been doing so far and we have planned for the coming months. Come and hear more about the scheme, including an additional river crossing providing a circular walking route and environmental enhancements, such as the creation of wet woodland, crassula management (in conjunction with RSPB), tree planting, tree and hedgerow management and creation of new habitats in areas where we are taking material to build the embankment.

The main aspects of this phase include the building of a new embankment, installation of the river outlet and temporarily re-diverting the river.

The scheme, costing just over £32 million, is part of the Environment Agency’s programme of £2.6 billion investment into flood defences across the country. The scheme was made possible through funding contributions from Birmingham City Council, Regional Flood and Coastal Committee, Arts Council and crowd-funding.

The first phase of the scheme was completed in spring 2017. Following improvements to the existing upstream flood storage area at Perry Hall Playing Fields, Phase 1 delivered improvement works in Perry Barr and Witton, including wall repairs and wall raising along Brookvale Road, construction of walls along Tame Road and installation of a flood gate at the Atlas Industrial Estate entrance. These measures in isolation do not provide a big enough reduction in flood risk, although they did successfully prevent properties from flooding in May 2018, so Phase 2 will provide the necessary flood water storage during a major flood, such as that experienced in 2007.

Along with flood defences and flood management schemes, knowing your flood risk is also important when protecting your family and property from flooding. People can check their risk and register to receive free flood warnings by visiting our page on preparing for flooding or calling Floodline on 0345 988 1188.

Link: Press release: Come along to flood scheme update at Forge Mill Farm
Source: Environment Agency

Press release: Traffic commissioners report on improved service to industry and better targeting of the most serious offenders

The Traffic Commissioners for Great Britain have used their latest annual report to highlight progress in reducing application processing times.

Between 2016/17 and 2017/18, the average time for a decision reduced from over 11 weeks to just over 7 weeks.

In addition, 90.2% of digital licence applications were granted within seven weeks against the published service standards provided.

Operators and applicants who apply digitally should now benefit from time savings, swifter correspondence and an intuitive application process that’s designed to make sure more complete information is provided.

In his foreword to the report, the Senior Traffic Commissioner for Great Britain, Richard Turfitt, says the regulators’ approach better supports innovation and economic growth. He goes on to add that whilst there is relative safety on our roads this does not mean there is room for complacency when it comes to compliance standards.

In 2017/18, the commissioners held 971 hearings into businesses reported for safety or licensing breaches, taking action to prevent the most serious offenders from running vehicles in the future.

The annual report reflects on the real and potential consequences of failing to keep vehicles properly maintained, using the example of an operator who is trusted to transport schoolchildren.

The report says: “It will be hard for anyone to understand why some operators believe it is acceptable to take our children to school in vehicles that are plainly dangerous.

The commissioners call on those responsible for procurement to make sure quality and compliance are foremost in their considerations.

The regulators expect compliance from every operator, saying: “There is no place in our industry for the people who operate vehicles this way and we take decisive action when these licence holders are brought to our attention.”

Their role as gatekeepers to the industry and the importance of maintaining a level playing field also feature prominently in the report.

“The vast majority of HGV and PSV operations are committed to running safe vehicles and working within the rules,” the regulators state.

“A licence holder is entitled to assume that when they bid for work, a competitor will not be able to get that contract as a result of cutting corners, especially where safety is concerned.”

The commissioners recognise the efforts of operators who work hard to meet safety and licensing standards and set out their commitment to engage with business at industry events and meetings.

“Operators who get things right – who abide by the daily discipline of carrying out checks and completing paperwork – need reassurance and guidance to stay compliant,” the report points out.

However, in dealing with those in the ‘long under-performing tail’ of the industry, the commissioners find the underlying causes to be poor management and a failure to access proper guidance.

They urge transport managers – who occupy a key role in the industry – to keep their knowledge and skills up to date through refresher training. But they also remind businesses to make sure the transport managers they employ are doing the job properly – otherwise they could lose their permission to run vehicles.

The report examines the other activities commissioners have been focusing on in order to deliver their strategic objectives.
This includes:

  • working to reduce the time it takes to get serious offenders to a hearing for potential action
  • publishing average application processing times on GOV.UK
  • publishing their written decisions on GOV.UK
  • commissioning a study of how effective their sanctions are

The report concludes by reinforcing the critical role played by others in support of traffic commissioners. It recognises the importance of the Driver and Vehicle Standards Agency (DVSA) in providing evidence for sound regulatory decisions to be made. The report also addresses the need for proper resourcing of the Office of the Traffic Commissioner.

Press enquiries

Media office
Office of the Traffic Commissioner

Suite 6

Stone Cross Place

Stone Cross Lane North

Golborne

Warrington

WA3 2SH

Link: Press release: Traffic commissioners report on improved service to industry and better targeting of the most serious offenders
Source: Gov Press Releases

The A4042 Trunk Road (Court Farm Roundabout, Torfaen to Hardwick Roundabout, Monmouthshire) (Temporary Speed Restrictions and No Overtaking) Order 2018 / Gorchymyn Cefnffordd yr A4042 (Cylchfan Court Farm, Torfaen i Gylchfan Hardwick, Sir Fynwy) (Cyfyngiadau Cyflymder Dros Dro a Dim Goddiweddyd) 2018

Link:

The A4042 Trunk Road (Court Farm Roundabout, Torfaen to Hardwick Roundabout, Monmouthshire) (Temporary Speed Restrictions and No Overtaking) Order 2018 / Gorchymyn Cefnffordd yr A4042 (Cylchfan Court Farm, Torfaen i Gylchfan Hardwick, Sir Fynwy) (Cyfyngiadau Cyflymder Dros Dro a Dim Goddiweddyd) 2018

Source: Legislation .gov.uk

The A487 Trunk Road (Pentood, south of Cardigan, Ceredigion) (Temporary 30 mph Speed Limit & No Overtaking) Order 2018 / Gorchymyn Cefnffordd yr A487 (Pentood, man i’r de o Aberteifi, Ceredigion) (Terfyn Cyflymder 30 mya Dros Dro a Dim Goddiweddyd) 2018

Link:

The A487 Trunk Road (Pentood, south of Cardigan, Ceredigion) (Temporary 30 mph Speed Limit & No Overtaking) Order 2018 / Gorchymyn Cefnffordd yr A487 (Pentood, man i’r de o Aberteifi, Ceredigion) (Terfyn Cyflymder 30 mya Dros Dro a Dim Goddiweddyd) 2018

Source: Legislation .gov.uk

The M4 Motorway (Slip Roads at Junction 28 (Tredegar Park), Newport) (Temporary 40 mph Speed Limit) Order 2018 / Gorchymyn Traffordd yr M4 (Y Ffyrdd Ymuno ac Ymadael wrth Gyffordd 28 (Parc Tredegar), Casnewydd) (Terfyn Cyflymder 40 mya Dros Dro) 2018

Link:

The M4 Motorway (Slip Roads at Junction 28 (Tredegar Park), Newport) (Temporary 40 mph Speed Limit) Order 2018 / Gorchymyn Traffordd yr M4 (Y Ffyrdd Ymuno ac Ymadael wrth Gyffordd 28 (Parc Tredegar), Casnewydd) (Terfyn Cyflymder 40 mya Dros Dro) 2018

Source: Legislation .gov.uk